Question 1
At a restaurant ice machine, the bin's meltwater drain ends below the floor sink's flood-level rim but above the standing water in its trap. The installer calls this an air break and says it is sufficient because the floor sink is separately trapped and vented. Under the 2018 IPC, how should the meltwater connection be corrected?
Show answer & explanation
Correct answer: D - Terminate the waste above the flood-level rim with the required air gap.